Guide for owners and building managers
Insulating a condominium building: from the owners' meeting to the works, without surprises
Cold façade, mould in the corners and a meeting to win over? This guide explains which majority you need, what each flat pays, the three ways to insulate a building and what the quote should include so the owners' meeting can decide.
By David Francisco, civil engineer at EnergyEase · Updated October 2026
For your owners' meeting
A proposal in the condominium's name and tax number, with the options side by side
An estimated cost per flat, based on the building's permillage
Cavity fill, flat by flat or external insulation: we tell you what suits your building
TF
Tomás F.Work in a flat, in an apartment building
“All the documents for the work (the quote, the technical data sheets for the materials, the work report, invoices and receipts) were duly handed to me.”
Public Google review, translated from Portuguese
Free, no obligation
Get a proposal for your owners' meeting
We visit the building, look inside the walls with a camera and send the quote in the condominium's name, with no obligation. You can ask as an owner or as the building manager.
Pick an option and see what changes on the building. Which one fits depends on the walls, the budget and what the owners' meeting approves.
Empty cavity
Today
The cavity is empty
Through the façade
Keeps the façade
Blown-in cavity insulation
We fill the cavity of double walls with water-repellent mineral wool, through 37 mm holes that we seal at the end. The façade keeps its design and materials.
Per m², incl. VAT18–35 €holes sealed; scaffolding quoted separately
DurationA few daysabout 200 m² in 3 days
Good to know
Approval: Owners' meeting, because the façade is a common part. It may be treated as an innovation: prepare the vote for the stricter majority.
Fits when: The walls have a cavity of at least 4 cm. Not every building has one: we check with the camera.
For owners who want to go ahead in their own home: an insulated lining wall, an insulated ceiling on the top floor or, where the wall has a cavity, blown-in insulation from the inside.
Per m², incl. VAT20–45 €blown-in; lining wall 70–150 € with painting
Duration1 dayper flat, with blown-in
Good to know
Coordination: Work done inside your home. We agree the dates and hours with you and, at the visit, tell you what to let the building manager know.
Fits when: To insulate inside your own flat: a lining wall or a false ceiling.
Insulation boards glued and fixed to the outside, with mesh and render on top, known in Portugal as capoto. It is the most complete option: it also covers pillars, beams and slab edges.
Per m², incl. VAT60–80 €painting included; scaffolding quoted separately
Duration3 to 6 weeksin a typical building
Good to know
Approval: Owners' meeting. Because it changes the look of the façade, plan for two thirds of the building's value.
Fits when: The walls are single or cavity walls and the building also wants to treat thermal bridges.
Indicative prices for building façades, VAT included. Scaffolding is not included: it is quoted separately depending on the building's height, as is the street-occupation permit. Outside Greater Lisbon, the quote also includes travel. See the prices per technique. The final price is the one in the written quote, after the visit.
Real project
A building in Cascais: mineral wool in the cavity, through the façade
A residential building in Cascais, built in the 1980s or 1990s, with condensation in the flats. The condominium had a quote for external insulation on the table.
At the visit we saw with the camera that the walls had a cavity. We blew mineral wool in through both façades from the scaffolding, sealed the holes, and at the end the façade was painted.
1Blowing mineral wool into the cavity2Sealing the holes3Façade painted
Costs
What insulating the building costs, per flat
Change the numbers and see an estimate for the building and for each owner. The starting values are those of a typical building that asks us for a quote: about 280 m² of façade and 8 flats.
‰
Cavity fill
if there is a cavity; scaffolding extra
Building
€5,040 – €9,800
Per flat, on average
€630 – €1,225
Your flat
External (ETICS)
painting included; scaffolding extra
Building
€16,800 – €22,400
Per flat, on average
€2,100 – €2,800
Your flat
Estimate with VAT included, to compare options; the exact rate is shown in the quote. For external insulation it includes painting; for cavity fill, sealing the holes. Scaffolding is not included: it is quoted separately depending on the building's height. The written quote, after the visit, confirms the price for your building.
It is one of the questions we hear most. There are several ways to make the levy lighter:
Swipe to see more →
Special levy in instalmentsThe meeting can approve payment over several months instead of one lump sum. Propose the schedule in the vote itself.
Reserve fundIt is compulsory: each owner pays at least 10% of their share of the charges. It is meant for conservation work and can cover part of the job. If it is used for anything else, it has to be topped up within 12 months. Check the balance with the building manager.
Work in phasesStart with the coldest or most run-down façade and do the others later. It spreads the effort, though the total ends up a little higher.
Compare the optionsWhere the walls have a cavity, cavity fill costs about half of external insulation, or less. At the visit we tell you if that is the case for your building.
If the levy does not fit an owner's budget, it is better to talk to the building manager before the meeting than after.
The rules
Condominium law: which majority do you need?
The rules are in the Portuguese Civil Code, in the articles on buildings divided into units (propriedade horizontal), as amended by Law 8/2022. The majority depends on the type of work, not the technique. Note: many English guides say "a simple majority (51%)" is always enough. For innovations and changes to the façade it is not.
Type of work
Majority needed
Article
ConservationRepairing and maintaining what is there
More than half of the building's permillage (at a second call, a majority of those present, if they represent at least 1/4)
1432
InnovationAdds something new to the common parts
Majority of the owners representing 2/3 of the building's total value
1425
Changes the façadeAlters the architectural line or the look of the building, like capoto
2/3 of the building's total value
1422(3)
UrgentEssential and urgent repairs to the common parts
Can go ahead without waiting for a meeting; if the building manager is absent, any owner can have them done
1427
The most debated point
Is insulation conservation or an innovation?
The law does not decide it case by case and court decisions are not unanimous. If the work repairs a run-down façade, some treat it as conservation; if it adds insulation where there was none, it tends to be seen as an innovation. If in doubt, prepare the vote for the stricter majority and check with the building manager or a lawyer.
Façade works step by step: from diagnosis to works
The annual owners' meeting takes place in the first half of January (or in the first quarter, if the regulations allow it or the meeting approves it). To put the works to a vote at that meeting, the preparation starts in the autumn. You can also call an extraordinary meeting at any time of the year.
Swipe to see the 6 steps →
1October and November
Diagnosis
Technical visit to the building: type of walls, cavity, state of the façade and roof, and where any damp comes from.
2November
Three comparable quotes
Since Law 8/2022, the building manager presents at least three quotes from different companies for major conservation work or innovations, unless the regulations or the meeting decide otherwise (art. 1436). Ask for them with the same description so you can compare them.
3At least 10 days before
Meeting notice
With a clear item on the agenda, for example: "Discussion and vote on thermal insulation works on the façades, based on the attached quotes".
4January
Owners' meeting and minutes
Discussion and vote. The minutes record the option chosen, the amount approved, the company and the payment schedule.
5Before the works
Permits and notice to residents
For external insulation, check with the municipality whether a notification or licence is needed, and apply for the street-occupation permit for the scaffolding. Tell residents the dates and working hours.
6After approval
Works
Cavity fill: a few days. External insulation: 3 to 6 weeks. At the end, photos and a work report.
The quote
What the quote for the owners' meeting should include
Building managers always ask us for the same things. Use this list to compare quotes, ours included.
Measured areas to insulate, per façade
System, brand and thickness of the insulation
Façade preparation and crack repair
Trims at windows, balconies, sills and shutter boxes
Scaffolding and street-occupation permit
Final painting included or as an option
VAT rate on each line
Duration and payment terms
Legal guarantee, licence and insurance of the company
Technical data sheets of the materials
Valid until the date of the meeting
In the condominium's name and tax number
In the EnergyEase proposal
A proposal ready for the owners' meeting
In the condominium's name and tax number (NIF)
The possible options side by side, in one document
Estimated cost per flat, if you send us the permillage
VAT on condominium works: when it is 6% and when 23%
6% / 23%
Conservation, repair and renovation work on residential buildings, including the common parts, can be charged at 6% VAT (item 2.27 of List I of the Portuguese VAT Code), as long as it is done under a works contract and the building is used for housing.
Two rules to watch. If materials exceed 20% of the value of the work, only the labour stays at 6% and the materials are charged at 23%, provided the invoice shows them separately; with a single global price, the whole job is charged at 23%. And in buildings with shops or offices, the non-residential part is charged at 23% and must be shown separately.
So the right rate depends on the work and the building. Our indicative prices already include VAT; the quote shows the rate for each line and why.
Do not confuse it with the 6% rate for renewable energy equipment, which ended in June 2025. Item 2.27 is still in force.
We know of no national programme currently open to condominiums.
In Amadora, the municipal REABILITA programme supports condominiums with thermal insulation of roofs and outside walls: up to 30% of the cost, with a maximum of €15,000. The building must have an occupancy licence at least 15 years old and at least half of its units used as homes. It asks for the minutes, the quote and the material specifications, and the grant is paid after the works and the inspection. Check with the municipality whether applications are open.
If a new programme opens, we issue the quote in the condominium's name and tax number, as calls usually require.
“An excellent experience! The whole process was very quick, from the reply to our first contact to carrying out the work. The technical team was very friendly, professional and transparent, always taking care to explain the work being done.”
Duarte N. · Google, translated from Portuguese
“Everything went as expected. The team was super professional and careful, and especially attentive to the daily clean-up after finishing the work. Small details, but they make a difference. Communication was always easy, with nothing to fault. I would hire them again, highly recommended.”
Andreia F. · Google, translated from Portuguese
“Work done to solve a condensation problem. Now that the critical time of year has arrived, with lower temperatures, there is no trace of it. Impeccable professionals, focused on perfection rather than speed.”
Teresa C. · Google, translated from Portuguese
Questions
Frequently asked questions about condominium works and insulation
Another question? Call 210 270 937 or message us on WhatsApp.
What majority is needed to approve insulation works in a condominium?
It depends on the work. Conservation work is approved by more than half of the building's permillage (at a second call, a majority of those present is enough if they represent at least a quarter). An innovation needs a majority of the owners representing two thirds of the building's total value (art. 1425 of the Civil Code). Work that changes the look of the façade, such as external insulation, needs the meeting's approval by two thirds of the building's total value (art. 1422(3)). Cavity fill does not change the façade, but it may be treated as an innovation: if in doubt, prepare the vote for the stricter majority.
Who pays: also owners who voted against, shops and garages?
As a rule, yes. Each owner pays in proportion to the value of their unit, the permillage (art. 1424), and that includes shops and garages, because the outside walls are common parts (art. 1421); it is only different if the deed says otherwise. Owners who voted against pay too, if the work is approved with the required majority. For innovations, an owner who did not approve is only exempt if a court finds the refusal justified, for example for luxury work or work out of proportion to the building (art. 1426). A decision that breaks the law or the regulations can be annulled at the request of an owner who did not approve it (art. 1433).
How much does it cost to insulate a building, per flat?
For a building with 280 m² of façade and 8 flats, cavity fill costs about €5,040 to €9,800 (€630 to €1,225 per flat) and external insulation about €16,800 to €22,400 (€2,100 to €2,800 per flat), VAT included. These amounts do not include scaffolding, which is quoted separately depending on the building's height. They are indicative figures: the final price depends on the building and comes after the technical visit.
Cavity fill or external insulation: which to choose for the building?
It depends on the walls. If they have a cavity of at least 4 cm, cavity fill costs about half of external insulation, or less, takes a few days and keeps the look of the façade. External insulation is the most complete solution: it also covers pillars, beams and slab edges and suits single or double walls, but it changes the look of the façade and needs two thirds of the building's total value at the meeting. Many old buildings in Lisbon have stone walls without a cavity and, in protected areas, external insulation may not be allowed: there, the route is the roof and insulating from the inside. Each owner can also insulate just their own flat from the inside, with an insulated lining wall, an insulated ceiling on the top floor or, if there is a cavity, blown-in insulation from the inside. At the visit we check the walls with a camera and tell you what suits your building.
Do we need a permit from the municipality?
For cavity fill, generally not: the façade keeps its shape and materials, and the RJUE (the Portuguese planning and building code) exempts conservation works and works of minor urban-planning relevance from a licence and from prior notification (arts. 6 and 6-A); check with the municipality how it classifies the work. For listed buildings, their protection zones or where municipal rules apply, the rules can be stricter. For external insulation it depends on the building and the municipality: a prior notification or a licence may be needed, especially in protected areas. Scaffolding on a public street needs a street-occupation permit from the municipality.
How long does it take to insulate a building?
With cavity fill, a few days: about 200 m² of façade in 3 days. External insulation takes 3 to 6 weeks. Add the time to decide: between the quote and the works there are often two to three months, because of the meeting.
Does insulation fix leaks?
No. Insulation helps against condensation, because the walls get less cold on the inside: these are the stains in corners, around windows and behind furniture that get worse on cold days. Stains that get worse after rain are a leak: the façade, the roof or the window frames are repaired first. Damp in the lower part of ground-floor walls, with salt deposits, comes from the ground and is dealt with first, by a specialist. We do not do waterproofing: if the visit shows a leak, we tell you before quoting. See our guide to cold and damp homes.
How do I know the cavity was properly filled?
We photograph the façade before we start and at the end. During the work you can ask us at any time to look inside the wall together with the endoscopic camera, and you can count the bags of wool that go into the wall.
Don't just take our word for it - hear from those who have experienced the EnergyEase difference.
I am very satisfied with the results so far. The change was noticeable right after the completion of the intervention.
João Baptista
Setubal, Portugal
Excellent result, completely satisfied.
Maria Ribeiro
Lisbon, Portugal
Everything went as expected. The team was extremely professional, careful, and especially attentive to daily cleaning after finishing the work. Small details that make a difference. Communication was always easy and flawless. I would hire them again—highly recommended.
Andreia Ferreira
Setubal, Portugal
Tomás Rodrigues
Normalmente responde em cerca de 1 hora
Olá, bem-vindo à EnergyEase! 👋
Sou o Tomás. Tem dúvidas sobre isolamento ou quer um orçamento gratuito? Fale connosco por WhatsApp, chamada ou e-mail. Teremos todo o gosto em ajudar!